General Conditions 102 (2013-10-15) - Medium to High Complexity - Services - Part III

31 Suspension of the Work

  1. The Contracting Authority may at any time, by written notice, order the Contractor to suspend or stop the Work or part of the Work under the Contract for a period of up to one hundred eighty (180) days. T he Contractor must immediately comply with any such order in a way that minimizes the cost of doing so. While such an order is in effect, the Contractor must not remove any part of the Work from any premises without first obtaining the written consent of the Contracting Authority. Within these one hundred eighty (180) days, the Contracting Authority must either cancel the order or terminate the Contract, in whole or in part, under section 28 or section 29.
  2. When an order is made under subsection 1, unless the Contracting Authority terminates the Contract by reason of default by the Contractor or the Contractor abandons the Contract, the Contractor will be entitled to be paid its additional costs incurred as a result of the suspension plus a fair and reasonable profit.
  3. When an order made under subsection 1 is cancelled, the Contractor must resume work in accordance with the Contract as soon as practicable. If the suspension has affected the Contractor's ability to meet any delivery date under the Contract, the date for performing the part of the Work affected by the suspension will be extended for a period equal to the period of suspension plus a period, if any, that in the opinion of the Contracting Authority, following consultation with the Contractor, is necessary for the Contractor to resume the Work. Any equitable adjustments will be made as necessary to any affected conditions of the Contract.

32 Default by the Contractor

  1. If the Contractor is in default in carrying out any of its obligations under the Contract, the Contracting Authority may, by giving written notice to the Contractor, terminate for default the Contract or part of the Contract. The termination will take effect immediately or at the expiration of a cure period specified in the notice, if the Contractor has not cured the default to the satisfaction of the Contracting Authority within that cure period.
  2. If the Contractor becomes bankrupt or insolvent, makes an assignment for the benefit of creditors, or takes the benefit of any statute relating to bankrupt or insolvent debtors, or if a receiver is appointed under a debt instrument or a receiving order is made against the Contractor, or an order is made or a resolution passed for the winding down of the Contractor, the Contracting Authority may, to the extent permitted by the laws of Canada, by giving written notice to the Contractor, immediately terminate for default the Contract or part of the Contract.
  3. If Canada gives notice under subsection 1 or 2, the Contractor will have no claim for further payment except as provided in this section. The Contractor will be liable to Canada for all losses and damages suffered by Canada because of the default or occurrence upon which the notice was based, including any increase in the cost incurred by Canada in procuring the Work from another source. The Contractor agrees to repay immediately to Canada the portion of any advance payment that is unliquidated at the date of the termination.
  4. Upon termination of the Contract under this section, the Contracting Authority may require the Contractor to deliver to Canada, in the manner and to the extent directed by the Contracting Authority, any completed parts of the Work, not delivered and accepted before the termination and anything the Contractor has acquired or produced specifically to perform the Contract. In such a case, subject to the deduction of any claim that Canada may have against the Contractor arising under the Contract or out of the termination, Canada will pay or credit to the Contractor:
    1. the value, of all completed parts of the Work delivered to and accepted by Canada, based on the Contract Price, including the proportionate part of the Contractor's profit or fee included in the Contract Price; and
    2. the cost to the Contractor that Canada considers reasonable in respect of anything else delivered to and accepted by Canada.
    The total amount paid by Canada under the Contract to the date of the termination and any amount payable under this subsection must not exceed the Contract Price.
  5. Title to everything for which payment is made to the Contractor will, once payment is made, pass to Canada unless it already belongs to Canada under any other provision of the Contract.
  6. If the Contract is terminated for default under subsection 1, but it is later determined that grounds did not exist for a termination for default, the notice will be considered a notice of termination for convenience issued under subsection 1 of section 29.

33 Termination for Convenience

  1. At any time before the completion of the Work, the Contracting Authority may, by giving notice in writing to the Contractor, terminate for convenience the Contract or part of the Contract. Once such a notice of termination for convenience is given, the Contractor must comply with the requirements of the termination notice. If the Contract is terminated in part only, the Contractor must proceed to complete any part of the Work that is not affected by the termination notice. The termination will take effect immediately or, as the case may be, at the time specified in the termination notice.
  2. If a termination notice is given pursuant to subsection 1, the Contractor will be entitled to be paid, for costs that have been reasonably and properly incurred to perform the Contract to the extent that the Contractor has not already been paid or reimbursed by Canada. The Contractor will be paid:
    1. on the basis of the Contract Price, for all completed work that is inspected and accepted in accordance with the Contract, whether completed before, or after the termination in accordance with the instructions contained in the termination notice;
    2. the Cost to the Contractor plus a fair and reasonable profit for all work terminated by the termination notice before completion; and
    3. all costs incidental to the termination of the Work incurred by the Contractor but not including the cost of severance payments or damages to employees whose services are no longer required, except wages that the Contractor is obligated by statute to pay.
  3. Canada may reduce the payment in respect of any part of the Work, if upon inspection, it does not meet the requirements of the Contract.
  4. The total of the amounts, to which the Contractor is entitled to be paid under this section, together with any amounts paid, due or becoming due to the Contractor must not exceed the Contract Price. The Contractor will have no claim for damages, compensation, loss of profit, allowance arising out of any termination notice given by Canada under this section except to the extent that this section expressly provides. The Contractor agrees to repay immediately to Canada the portion of any advance payment that is unliquidated at the date of the termination.

34 Dispute Resolution

The parties agree that, both during and after the performance of the work under the contract, each of them shall make bona fide efforts to resolve any disputes arising between them by negotiation. In the event that the parties cannot resolve a dispute through negotiation, they agree to submit the dispute to mediation. The parties will jointly select a mediator and will bear the cost of mediation equally. In the event that one or more issues remain in dispute following completion of the mediation, then the parties agree to submit those issues to binding arbitration pursuant to the Commercial Arbitration Act.

35 Accounts and Audit

  1. The Contractor must keep proper accounts and records of the cost of performing the Work and of all expenditures or commitments made by the Contractor in connection with the Work, including all invoices, receipts and vouchers. The Contractor must retain records, including bills of lading and other evidence of transportation or delivery, for all deliveries made under the Contract.
  2. If the Contract includes payment for time spent by the Contractor, its employees, representatives, agents or subcontractors performing the Work, the Contractor must keep a record of the actual time spent each day by each individual performing any part of the Work.
  3. Unless Canada has consented in writing to its disposal, the Contractor must retain all the information described in this section for six (6) years after it receives the final payment under the Contract, or until the settlement of all outstanding claims and disputes, whichever is later. During this time, the Contractor must make this information available for audit, inspection and examination by the representatives of Canada, who may make copies and take extracts. The Contractor must provide all reasonably required facilities for any audit and inspection and must furnish all the information as the representatives of Canada may from time to time require to perform a complete audit of the Contract.
  4. The amount claimed under the contract, calculated in accordance with the Basis of Payment provision in the Articles of Agreement, is subject to government audit both before and after payment is made. If an audit is performed after payment, the Contractor agrees to repay any overpayment immediately on demand by Canada. Canada may hold back, deduct and set off any credits owing and unpaid under this section from any money that Canada owes to the Contractor at any time (including under other contracts). If Canada does not choose to exercise this right at any given time, Canada does not lose this right.

36 Right of Set-off

Without restricting any right of set-off given by law, Canada may set-off against any amount payable to the Contractor under the Contract, any amount payable to Canada by the Contractor under the Contract or under any other current contract. Canada may, when making a payment pursuant to the Contract, deduct from the amount payable to the Contractor any such amount payable to Canada by the Contractor which, by virtue of the right of set- off, may be retained by Canada.

37 Notice

Any notice under the Contract must be in writing and may be delivered by hand, courier, mail, facsimile or other electronic method that provides a paper record of the text of the notice. It must be sent to the Party for whom it is intended at the address stated in the Contract. Any notice will be effective on the day it is received at that address. Any notice to Canada must be delivered to the Contracting Authority.

38 Conflict of Interest and Values and Ethics Codes for the Public Service

The Contractor acknowledges that individuals who are subject to the provisions of the Conflict of Interest Act, 2006, c. 9, s. 2, the Conflict of Interest Code for Members of the House of Commons, the Values and Ethics Code for the Public Service or all other codes of values and ethics applicable within specific organizations cannot derive any direct benefit resulting from the Contract.

39 No Bribe or Conflict

  1. The Contractor declares that no bribe, gift, benefit, or other inducement has been or will be paid, given, promised or offered directly or indirectly to any official or employee of Canada or to a member of the family of such a person, with a view to influencing the entry into the Contract or the administration of the Contract.
  2. The Contractor must not influence, seek to influence or otherwise take part in a decision of Canada knowing that the decision might further its private interest. The Contractor must have no financial interest in the business of a third party that causes or would appear to cause a conflict of interest in connection with the performance of its obligations under the Contract. If such a financial interest is acquired during the period of the Contract, the Contractor must immediately declare it to the Contracting Authority.
  3. The Contractor warrants that, to the best of its knowledge after making diligent inquiry, no conflict exists or is likely to arise in the performance of the Contract. In the event the Contractor becomes aware of any matter that causes or is likely to cause a conflict in relation to the Contractor's performance under the Contract, the Contractor must immediately disclose such matter to the Contracting Authority in writing.
  4. If the Contracting Authority is of the opinion that a conflict exists as a result of the Contractor's disclosure or as a result of any other information brought to the Contracting Authority's attention, the Contracting Authority may require the Contractor to take steps to resolve or otherwise deal with the conflict or, at its entire discretion, terminate the Contract for default. Conflict means any matter, circumstance, interest, or activity affecting the Contractor, its personnel or subcontractors, which may or may appear to impair the ability of the Contractor to perform the Work diligently and independently.

40 Survival

All the Parties' obligations of confidentiality, representations and warranties set out in the Contract as well as the provisions, which by the nature of the rights or obligations might reasonably be expected to survive, will survive the expiry or termination of the Contract.

41 Severability

If any provision of the Contract is declared by a court of competent jurisdiction to be invalid, illegal or unenforceable, that provision will be removed from the Contract without affecting any other provision of the Contract.

42 Successors and Assigns

The Contract is to the benefit of and binds the successors and permitted assignees of Canada and of the Contractor.

43 Contingency Fees

The Contractor certifies that it has not directly or indirectly, paid or agreed to pay and agrees that it will not, directly or indirectly, pay a contingency fee for the solicitation, negotiation or obtaining of the Contract to any person, other than an employee of the Contractor acting in the normal course of the employee's duties. In this section, "contingency fee" means any payment or other compensation that depends or is calculated based on a degree of success in soliciting, negotiating or obtaining the Contract and "person" includes any individual who is required to file a return with the registrar pursuant to section 5 of the Lobbyist Registration Act, R.S. 1985, c. 44 (4th Supplement).

44 International Sanctions

  1. Persons in Canada, and Canadians outside of Canada, are bound by economic sanctions imposed by Canada. As a result, the Government of Canada cannot accept delivery of goods or services that originate, either directly or indirectly, from the countries or persons subject to economic sanctions.
  2. The Contractor must not supply to the Government of Canada any goods or services which are subject to economic sanctions.
  3. The Contractor must comply with changes to the regulations imposed during the period of the Contract. The Contractor must immediately advise Canada if it is unable to perform the Work as a result of the imposition of economic sanctions against a country or person or the addition of a good or service to the list of sanctioned goods or services. If the Parties cannot agree on a work around plan, the Contract will be terminated for the convenience of Canada in accordance with section 29.

45 Code of Conduct and Certifications - Contract

  1. The Contractor agrees to comply with the Code of Conduct for Procurement and to be bound by its terms. In addition to complying with the Code of Conduct for Procurement, the Contractor must also comply with the terms set out in this section.
  2. The Contractor further understands that, to ensure fairness, openness and transparency in the procurement process, the commission of certain acts or offences may result in a termination for default under the Contract. If the Contractor made a false declaration in its bid, makes a false declaration under the Contract, fails to diligently maintain up to date the information herein requested, or if the Contractor or any of the Contractor's affiliates fail to remain free and clear of any acts or convictions specified herein during the period of the Contract, such false declaration or failure to comply may result in a termination for default under the Contract. The Contractor understands that a termination for default will not restrict Canada's right to exercise any other remedies that may be available against the Contractor and agrees to immediately return any advance payments.
  3. For the purpose of this section, everyone, including but not limited to organizations, bodies corporate, societies, companies, firms, partnerships, associations of persons, parent companies and subsidiaries, whether partly or wholly-owned, as well as individuals and directors, are Contractor's affiliates if:
    1. directly or indirectly either one controls or has the power to control the other, or
    2. a third party has the power to control both.
    Indicia of control, include, but are not limited to, interlocking management or ownership, identity of interests among family members, shared facilities and equipment, common use of employees, or a business entity created following the acts or convictions specified in this section which has the same or similar management, ownership, or principal employees, as the case may be.
  4. The Contractor must diligently maintain an up-to-date list of names by informing Canada in writing of any change occurring during the period of the contract. The Contractor must also, when so requested, provide Canada with the corresponding Consent Forms.
  5. The Contractor certifies that it is aware, and that its affiliates are aware, that Canada may verify the information provided by the Contractor, including the information relating to the acts or convictions specified herein through independent research, use of any government resources or by contacting third parties.
  6. The Contractor certifies that neither the Contractor nor any of the Contractor's affiliates have directly or indirectly, paid or agreed to pay, and will not, directly or indirectly, pay a contingency fee to any individual for the solicitation, negotiation or obtaining of the Contract if the payment of the fee would require the individual to file a return under section 5 of the Lobbying Act.
  7. The Contractor certifies that no one convicted under any of the provisions under a) or b) are to receive any benefit under the contract. In addition, the Contractor certifies that except for those offences where a criminal pardon or a record suspension has been obtained or capacities restored by the Governor in Council, neither the Contractor nor any of the Contractor's affiliates has ever been convicted of an offence under any of the following provisions:
    1. paragraph 80(1)(d) (False entry, certificate or return), subsection 80(2) (Fraud against Her Majesty) or section 154.01 (Fraud against Her Majesty) of the Financial Administration Act, or
    2. section 121 (Frauds on the government and Contractor subscribing to election fund), section 124 (Selling or Purchasing Office), section 380 (Fraud) for fraud committed against Her Majesty or section 418 (Selling defective stores to Her Majesty) of the Criminal Code of Canada, or
    3. section 462.31 (Laundering proceeds of crime) or sections 467.11 to 467.13 (Participation in activities of criminal organization) of the Criminal Code of Canada, or
    4. section 45 (Conspiracies, agreements or arrangements between competitors), 46 (Foreign directives) 47 (Bid rigging), 49 (Agreements or arrangements of federal financial institutions), 52 (False or misleading representation), 53 (Deceptive notice of winning a prize) under the Competition Act, or
    5. section 239 (False or deceptive statements) of the Income Tax Act, or
    6. section 327 (False or deceptive statements) of the Excise Tax Act, or
    7. section 3 (Bribing a foreign public official) of the Corruption of Foreign Public Officials Act, or
    8. section 5 (Trafficking in substance), section 6 (Importing and exporting), or section 7 (Production of substance) of the Controlled Drugs and Substance Act.

46 Harassment in the Workplace

  1. The Contractor acknowledges the responsibility of Canada to ensure, for its employees, a healthy work environment, free of harassment. A copy of the Treasury Board policy, the Policy on the Prevention and Resolution of Harassment in the Workplace, which is also applicable to the Contractor, is available on the Treasury Board Website.
  2. The Contractor must not, either as an individual, or as a corporate or unincorporated entity, through its employees or subcontractors, harass, abuse, threaten, discriminate against or intimidate any employee, contractor or other individual employed by, or under contract with Canada. The Contractor will be advised in writing of any complaint and will have the right to respond in writing. Upon receipt of the Contractor's response, the Contracting Authority will, at its entire discretion, determine if the complaint is founded and decide on any action to be taken.

47 Access to Information

Records created by the Contractor, and under the control of Canada, are subject to the Access to Information Act. The Contractor acknowledges the responsibilities of Canada under the Access to Information Act and must, to the extent possible, assist Canada in discharging these responsibilities. Furthermore, the Contractor acknowledges that section 67.1 of the Access to Information Act provides that any person, who destroys, alters, falsifies or conceals a record, or directs anyone to do so, with the intent of obstructing the right of access that is provided by the Access to Information Act is guilty of an offence and is liable to imprisonment or a fine, or both.

48 Green Procurement / Sustainable Development

In order to meet Canada's commitments under the Policy on Green Procurement, contractors are encouraged to:

  1. use paper containing fibre certified as originating from a sustainably-managed forest and containing minimum 30% recycled content;
  2. use an environmentally-preferable format including black and white printing instead of colour printing, printing double sided/duplex, using staples or clips instead of cerlox, duotangs or binders;
  3. Recycle unneeded printed documents (in accordance with Security Requirements);
  4. Distribute documents / deliverables electronically; and
  5. Use ENERGY STAR office equipment.

49 Entire Agreement

The Contract constitutes the entire and only agreement between the Parties and supersedes all previous negotiations, communications and other agreements, whether written or oral, unless they are incorporated by reference in the Contract. There are no terms, covenants, representations, statements or conditions binding on the Parties other than those contained in the Contract.